Topicselectricity-supply
Where the Electricity Comes From
A sourced reference collection on the supply side of the AI power problem — a closed nuclear reactor reopened on the strength of one buyer's twenty-year contract, hyperscalers ordering reactors that have never been built, gas turbine slots sold out to 2030, and the transformer queue that is the least glamorous item on the critical path.
- Assertions
- 8
- Sources consulted
- 13
- Read in full
- 5/13
- Cited as evidence
- 5
13 sources sit behind this page — including any that arrive with a concept this page shares with another collection. 5 were retrieved and read in full, and only those can back an assertion. 3 could not be retrieved, and 5 were surfaced and deliberately set aside. Every one of them is named in the register below, with the reason in view. How we source this.
Timeline newest first · evenly spaced, not to scale
Our own synthesis, written to orient you — not evidence. Every factual statement here is asserted and sourced further down this page.
The demand side of this problem has its own collection: how much electricity data centres use, how fast it is growing, and what regulators have done about it. This page is the other half — what is actually being built to serve that demand, and how long the physical equipment takes to arrive. Almost everything here reduces to lead time.
The clearest measure of what AI demand is worth to a generator is that it made a closed nuclear reactor worth reopening. Three Mile Island Unit 1 shut down in September 2019, prematurely, for poor economics — it had run at a 96.3% capacity factor in its final year, so the problem was price, not performance. Exactly five years later Constellation announced a restart as the Crane Clean Energy Center: 837 megawatts of capacity, approximately 835 returning to the grid, under a twenty-year power purchase agreement with Microsoft described as the largest in the company's history, expected in 2028 and subject to Nuclear Regulatory Commission approval. A plant uneconomic at merchant prices becomes economic when a single buyer will contract for two decades.
The stranger form of the same trade is buying reactors that do not exist. In October 2024 Google agreed to purchase electricity from a fleet of Kairos Power small modular reactors — up to 500 MW, first unit in 2030, deployments through 2035 — under a master plant development agreement with milestone-based accountability. Google described what it was buying as an orderbook of reactors: a commitment to a production line rather than to a plant, which is how a technology with high per-unit engineering cost is meant to become cheap. The design is fluoride salt-cooled, described as the first non-water-cooled reactor approved for construction in the United States in more than fifty years. For scale, Google has signed over 115 clean energy agreements totalling more than 14 GW since 2010, so 500 MW arriving in the 2030s is a strategically large bet and a numerically small one.
The fastest conventional route to firm capacity is a gas turbine, and those are now rationed by factory slots. Within the first quarter of 2026 GE Vernova's volume under contract rose from 83 to 100 gigawatts and its slot reservation agreements — reservations of future manufacturing capacity held ahead of firm orders — from 43 to 56, with 21 gigawatts of new agreements signed in three months. Roughly 10 gigawatts of 2029 capacity was available at the start of the quarter; by the end, roughly 10 remained across 2029 and 2030 together. Lead time on a heavy-duty machine is about three years. Data centres are 20% of that book and traditional utilities and industrials the other 80%, so this is not purely an AI phenomenon — but AI changed the rate, and new-order pricing is running 10 to 20 points higher per kilowatt than the previous quarter.
Generation is useless without the equipment that connects it, and that has the longest queue of all. Second-quarter 2025 survey averages: power transformers 128 weeks, generator step-up units 144 weeks, switchgear 44. Demand since 2019 rose 274% for generator step-up transformers and 119% for power transformers; prices rose 77% and 45%. Underneath it sits a replacement problem with nothing to do with AI — 40 million U.S. distribution transformers past their expected service life, 55% of in-service units over 33 years old. A transformer is not a sophisticated device. It is a large one, made of steel and copper by a small number of factories, and it sits on the critical path of everything else.
That last claim is disputed, and the dissent is carried here rather than dropped. A transformer broker quoted in the same reporting says flatly that there is no shortage, that standard substation units can be delivered in 12 to 14 months across all voltage classes, and that the scarcity is exaggerated to drive pricing — locating the bottleneck in utility qualification processes and approved-vendor lists rather than in factory capacity. Everyone arguing has an interest, including the analysts selling the research that reports a 30% deficit. Nothing read here settles it, but it changes what an average means: 128 weeks is consistent both with a real capacity shortfall and with a market where faster routes exist that most large buyers cannot use.
What is missing is named. The most legally consequential thing in this subject — the regulatory dispute over whether load co-located behind the meter at a nuclear plant should pay transmission charges — is absent entirely, because that source was not retrieved. So is on-site generation, the third strategy alongside contracts and grid connection, and the one with the sharpest local air-quality consequences. A larger small-modular-reactor commitment than the one described here was announced and not read, so this page understates the scale of what has been promised.
Figures
Every number below is asserted and sourced elsewhere on this page.
How long the grid equipment takes
Average lead times by equipment class. The two transformer classes are two and a half to nearly three years, which sets the schedule for everything downstream of them.
Average lead time, weeks
Switchgear
Power transformers
Generator step-up units
Second-quarter 2025 survey averages as reported in January 2026: 128 weeks for power transformers, 144 weeks for generator step-up units and 44 weeks for switchgear. The underlying survey sits behind commercial subscription and was not retrieved; these are the figures as reported. A practitioner quoted in the same article disputes them, stating standard substation units can be delivered in 12 to 14 months.
Demand growth since 2019, by equipment class
Why the queue formed. Generator step-up transformers — the units that connect a new power plant to the grid — grew nearly three times faster than distribution equipment.
Growth in demand since 2019, per cent
Distribution transformers
Substation power transformers
Power transformers
Generator step-up transformers
Growth in demand between 2019 and 2025 as reported in January 2026: 274% for generator step-up transformers, 119% for power transformers, 116% for substation power transformers and 34% for distribution transformers. Reported figures from a subscription survey that was not retrieved directly.
Concepts
The vocabulary this subject is built from, and what we can show about each.
Corporate Nuclear Procurement
otherConstellation announced on 20 September 2024 that it would restart Three Mile Island Unit 1 — shut in 2019 for poor economics despite a 96.3% capacity factor — as the 837 MW Crane Clean Energy Center under a 20-year power purchase agreement with Microsoft, expecting restart in 2028 subject to Nuclear Regulatory Commission approval.
1 source1 retrieved & read
- SupportsPrimary evidenceRetrieved & readConstellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid
Google agreed on 14 October 2024 to buy up to 500 MW from a fleet of Kairos Power small modular reactors, first unit in 2030 and deployment through 2035 — described as an orderbook of reactors rather than a plant, using a fluoride salt-cooled design whose demonstration unit received a construction permit in 2023, against Google's existing 14 GW of clean energy agreements.
2 sources2 retrieved & read
- SupportsPrimary evidenceRetrieved & readGoogle and Kairos Power Partner to Deploy 500 MW of Clean Electricity Generation
- SupportsPrimary evidenceRetrieved & readGoogle signs advanced nuclear clean energy agreement with Kairos Power
Data Centre Electricity Demand
othershared from another collection — see its own page for what it assertsData Centre Energy Mix
othershared from another collection — see its own page for what it assertsGrid Equipment Lead Times
otherSecond-quarter 2025 survey averages put power transformers at 128 weeks and generator step-up units at 144 weeks against 44 for switchgear, after demand rose 274% for GSUs and 119% for power transformers since 2019 and prices rose 77% and 45% — atop an installed base of 40 million U.S. distribution transformers beyond service life.
1 source1 retrieved & read
- SupportsRetrieved & readTransformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis?
A transformer broker quoted in the same reporting states there is no shortage, that standard substation units can be delivered in 12 to 14 months across all voltage classes, and that the scarcity is exaggerated to drive pricing — locating the bottleneck in utility qualification and vendor-list practices rather than factory capacity.
1 source1 retrieved & read
- QualifiesRetrieved & readTransformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis?
Grid Interconnection Constraint
othershared from another collection — see its own page for what it assertsThe Generation Equipment Queue
otherGE Vernova's first quarter of 2026 shows gas turbine volume under contract rising from 83 to 100 GW and slot reservations from 43 to 56 GW, with roughly 10 GW left across 2029 and 2030 combined, a three-year heavy-duty lead time, data centres at 20% of the book, and new-order pricing running 10 to 20 points higher per kilowatt than the previous quarter.
1 source1 retrieved & read
Timeline
What actually happened, in order, with sources.
- 3 United States
Where this topic’s events took place, as far as our sources establish it. Events with no single location — a standards publication, say — and events we have not yet attributed are both counted as unattributed rather than omitted.
Apr 23, 2026
Gas Turbine Slots Sell Out Through 2030
Reporting of 23 April 2026 records GE Vernova's gas turbine volume under contract rising from 83 to 100 GW in one quarter and slot reservations from 43 to 56 GW, leaving roughly 10 GW across 2029 and 2030 combined, on a three-year lead time, with data centres at 20% of the book and new-order pricing 10 to 20 points higher per kilowatt than the prior quarter.
1 source1 retrieved & read
Oct 14, 2024
A Buyer Orders Reactors That Do Not Exist Yet
Google and Kairos Power announced on 14 October 2024 a master plant development agreement for up to 500 MW of small modular reactors across a U.S. fleet, first unit in 2030 through 2035, described by Google as an orderbook of reactors — a fluoride salt-cooled design whose demonstration unit received a construction permit in 2023.
2 sources2 retrieved & read
- SupportsPrimary evidenceRetrieved & readGoogle and Kairos Power Partner to Deploy 500 MW of Clean Electricity Generation
- SupportsPrimary evidenceRetrieved & readGoogle signs advanced nuclear clean energy agreement with Kairos Power
Sep 20, 2024
A Closed Reactor Is Worth Reopening
Constellation announced on 20 September 2024 the restart of the former Three Mile Island Unit 1 as the 837 MW Crane Clean Energy Center under a 20-year power purchase agreement with Microsoft, expected in 2028 subject to regulatory approval — a plant closed in 2019 for poor economics despite a 96.3% capacity factor in its final year.
1 source1 retrieved & read
- SupportsPrimary evidenceRetrieved & readConstellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid
Source register
All 13 sources behind this page — what we read, what we tried to read and could not, and what we looked at and set aside, with the reason in view for each. A concept shared with another collection brings its own references with it, so some entries here were surfaced for a neighbouring topic rather than this one.
- Cited as evidence
- 5
- Tried, could not read
- 3
- Surfaced, set aside
- 5
Cited sources 5 distinct links
Original publisher links. Files open on the publisher’s site; we do not host copies. A linked document is not an additional source or an independent verification.
- Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid ↗
Constellation Energy · Published 2024-09-20
- Data centers drive record surge in GE Vernova power equipment orders as turbine slots tighten through 2030 ↗
Power Engineering · Published 2026-04-23
- Google and Kairos Power Partner to Deploy 500 MW of Clean Electricity Generation ↗
Kairos Power · Published 2024-10-14
- Google signs advanced nuclear clean energy agreement with Kairos Power ↗
Google · Published 2024-10-14
- Transformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis? ↗
POWER Magazine · Published 2026-01-02
Tried, could not read3
We attempted these and were refused or served nothing. Nothing on this page rests on them; they are published so the gaps are checkable rather than invisible.
Surfaced, set aside5
These came up while researching and were deliberately not used. We do not claim to have read them — each is listed with why it was passed over, so the shape of the survey is visible and not just its conclusions.
- Amazon and X-energy small modular reactor agreements
- Nuclear Regulatory Commission licensing record for the Crane Clean Energy Center restart
- On-site and behind-the-meter generation at data centre sites
- Talen Energy and Amazon Susquehanna nuclear arrangements
- Wood Mackenzie transformer and grid equipment supply surveys
Coverage & limits
What this page does and does not claim.
Thirteenth packet, and the supply-side companion to the Powering AI collection rather than an extension of it: that page covers demand and the policy response, this one covers what is being built and how long the equipment takes. Eleven sources were consulted: five were retrieved and read, one was retrieved and yielded no readable content, and five were surfaced and set aside with a stated reason. The one that yielded nothing is worth explaining rather than hiding — a quarterly filing was successfully downloaded from EDGAR but stores its text in a form no available tooling on this machine could extract, so the gas turbine figures here come from trade reporting of an earlier quarter's results rather than from the filing itself, and are one quarter stale. The nuclear material rests on primaries from both sides of each agreement, which is the right way to read a contract announcement: Constellation's own release for the restart, and both Google's and Kairos Power's for the small modular reactor fleet, each supplying detail the other omits. Company projections inside those releases — job counts, tax revenue, state GDP contributions — are recorded as projections and asserted nowhere; capacity, dates and contract terms are what is used. The equipment material is weaker by construction: the lead-time and deficit figures originate in a commercial survey that sits behind subscription and was not retrieved, so they reach this page through trade reporting of that survey, and the reporting is what is cited. That same article is the reason this collection carries a direct dissent — a transformer broker stating there is no shortage and that standard substation units can be delivered in 12 to 14 months, locating the bottleneck in utility qualification practice rather than factory capacity. It is recorded as a qualifying view with the interests on both sides stated, and it is not resolved, because nothing read here distinguishes a genuine capacity shortfall from a market whose faster routes most large buyers cannot use. Named gaps, in order of value: the regulatory dispute over transmission charges for load co-located behind the meter at a nuclear plant, which is the most legally consequential thing in this subject and is absent entirely; on-site and behind-the-meter generation, the third strategy alongside contracts and grid connection and the one with the sharpest local air-quality and permitting consequences, asserted nowhere; a larger announced small-modular-reactor commitment than the one described here, which means this page understates the scale of what has been promised; the underlying grid-equipment survey; and the regulator's own licensing record for the reactor restart, whose absence is why 2028 is described here as an expected rather than a scheduled date. Not yet editor-reviewed; every assertion reads as reported.
Source check, 2026-09-17. Numeric-presence checks passed for 8 assertions using available source text, which may be cached. This is not verification of their meaning. What this check does and does not prove →
- Not editor-reviewed unless labelled. Assertions marked Reported are assembled from the sources shown and have not yet been checked by an editor. Only Primary source and Corroborated mean a human verified them.
- Disagreements are preserved, not resolved. Where sources conflict, both accounts appear and the assertion is marked Disputed.
- Retrieval status is disclosed per source. A source we could not open is never counted as evidence for an assertion.
This page is also available as structured data: /api/v1/topics/electricity-supply